Company: Entergy Nuclear Operations, Inc.
Current Parent CompanyEntergy
Parent at the Time of the Penalty Announcement subscribe to see this data field
Penalty: $60,000
Year: 2005
Date: July 14, 2005
Offense Group: safety-related offenses
Primary Offense: nuclear safety violation
Violation Description: On July 14, 2005, a Notice of Violation and Proposed Imposition of Civil Penalty in the base amount of $60,000 for a Severity Level III problem consisting of three violations was issued. The violations involved the failure of the Control Room Supervisor (CRS), the Reactor Operator (RO), and the Shift Manager (SM) to follow the requirements in 10 CFR 26.20 and procedures in Technical Specification 5.4.1. The violations cited: (1) the CRS being asleep, and therefore, not in a condition to respond to plant conditions or emergencies (Violation A); (2) the RO observing the CRS asleep, but failing to take immediate actions to awaken the CRS, inform appropriate site personnel, and initiate a CR (Violation B.1) and the SM failing to inform appropriate site personnel and initiate a CR (Violation B.2); and (3) the CRS not being relieved of duty and for-cause FFD tested (Violation C).
Level of Government: federal
Action Type: agency action
Agency: Nuclear Regulatory Commission
Civil or Criminal Case: civil
Facility State: Massachusetts
HQ Country of Current Parent: USA
HQ State of Current Parent: Louisiana
Ownership Structure of Current Parent: publicly traded
Major Industry of Current Parent: utilities and power generation
Specific Industry of Current Parent: utilities
Source of Data(click here)
Source Notes: If an online information source is not working, check the Violation Tracker Data Sources page for an updated link.
Current parent company note: Parent-subsidiary relationship is current as of the most recent revision listed in the Update Log.